|
Shrouded Power
Tools Hit a Homerun at Pawtucket Baseball Stadium

A
$15 million public-private renovation project began the transformation
of an aging ballpark into a new state-of-the-art minor league complex
in Pawtucket, RI by opening day of baseball season. Planned improvements
to McCoy stadium include 3,000 more seats, new entrance tower, a
12-foot-high berm with picnic seating to ring the outfield, additional
parking lots and accessibility for the handicapped.
During
the bidding process, O. Ahlborg & Sons, the general contractor
was notified that the roof supports and corresponding beams contained
approximately 80,000 ft2 of old, lead-based paint which
requires strict control during removal to prevent release to the
environment. Abrasive blasting was evaluated for such a project,
but full containment, scaffolding, safety and ventilation systems
required by abrasive blasting techniques would be too costly. Chemical
strippers were evaluated but thought to be unpredictable. The potential
for multiple applications of stripper to remove the aged coatings
increased waste generation and 24-hour delay in removal of the stripper
was not desirable given the rigid time constraints of the project.
This highly visible project required a deleading contractor to utilize
dustless power tool cleaning technology to perform the lead-based
paint removal in preparation for a new coatings system.
Environmental
Contracting, a Providence-based deleading contractor, was selected
to perform the lead abatement and prepare the structural steel surfaces
for coatings application. "We were not awarded the project
solely on low price, we were awarded the project because of our
company's track record in utilizing Pentek's state-of-the-art technology,"
says Bill Tracey, President of Environmental Contracting, Inc.
The
first phase of the project involved the removal of lead paint from
the underside of the canopy which wraps the stadium from right to
left field and covers the majority of the seating in the stadium.
The work schedule demanded grueling double shifts to meet the opening
day schedule. A 100-foot crane was used to hoist two (2) Vac-Pac
Multi-Tool HEPA vacuum and waste collection systems
to the highest seating level. The system's capacity to control lead
dust and debris allowed Environmental Contracting's workers to operate
without containment and ventilation structures. Additionally they
were able to eliminate wind load problems of containments and minimized
daily set-up and tear down.
Pentek's
mobile Vac-Pac HEPA vacuum and waste collection systems, stationed
in the concourse of the stadium, provided the capability to run
up to 12 tools simultaneously. Environmental Contracting's ability
to quickly deploy and demobilize equipment, and flexibility in configuring
the system increased the productivity of the abatement project,
while permitting other phases of stadium construction to go on without
interruption.
Eleven
tool operators began stripping the steel beams and roof supports,
then repainted them. Workers were situated on JLG lifts with 50
foot reaches allowing them to attack the I-beams and support structures
with Roto-Peen
scalers and Corner
Cutter needles guns. The shrouded Roto-Peen scaler cleans flat
steel to a bare metal finish, while the needle gun has interchangeable
shrouds to tackle the intricate roof supports, bolts and rivets
as well as flat area surfaces. Each individual operator could quickly
change his tool by transferring the vacuum hose and airline to the
new tool. The hose lengths were taped off at strategic positions
so that the workers lifted only the tool itself, not the weight
of the airline and vacuum hoses. The ability to change out lightweight
tools rapidly or adjust the geometry of the shrouds meant workers
could efficiently abate all surfaces within their reach.
All
coatings were removed by the 100% mechanical system and conveyed
directly--via 150 ft., 1-1/2 inch vacuum hoses--into a 55-gallon
drum integral to the Vac-Pac unit. This process allowed the lead-based
waste to be sealed under negative pressure for a dustless changeout
to a new DOT-approved waste disposal drum. The
majority of the first phase was completed prior to opening day April
9, 1998. The second phase of this work involved lead paint removal
from the support structures beneath the stadium, and is being completed
as the early season progresses. The project demonstrates the successful
use of power tool cleaning under vacuum conditions. |