Abrasive blasting
is the traditional technique used on such structures, but the full
containment and ventilation systems required by abrasive blasting
techniques substantially increase costs. Full containment would
also disrupt the heavily-used highway, while tearing down the tarps
in the morning and erecting them again each night would drastically
impact on the hours available for deleading. For these reasons,
the New Jersey Department of Transportation (NJ DOT) opted for an
alternative process provided by Pentek, Inc., of Coraopolis, Penn.,
which eliminates expensive containment structures and maximizes
the time for cleaning and repainting. Pentek's dustless lead abatement
system was employed by CRX Environmental, a Pittsburgh-based deleading
and painting contractor, to remove and collect the hazardous lead-based
paint from steel I-beams and bearings, and concrete bridge abutments
on the Route 495 pedestrian bridge near Union City, New Jersey.
NJ DOT project
specifications made it clear that absolute control would be maintained
over lead-contaminated dust and debris during the project. A NJ
DOT project engineer was on site to verify that no discernible emissions
were produced, an acceptable surface preparation was achieved, and
new protective coatings were appropriately applied under acceptable
environmental conditions.
Pentek's mobile VAC-PAC
HEPA vacuum and waste collection system, stationed in the back of
a standard pickup truck 100 ft. from the bridge, provided the capability
to run up to 10 power tools simultaneously. Portable lights enabled
CRX technicians to work through the night, eliminating daytime traffic
interference. CRX's ability to quickly deploy and demobilize equipment
and to flexibly configure the Pentek system increased the productivity
of the abatement project while permitting almost normal traffic
flow. The work schedule was drawn up by CRX and NJ DOT to specifically
mitigate traffic problems: only one lane or entrance/exit ramp was
closed during off hours and all lanes opened for morning and evening
rush hour traffic. The Pentek system's capacity to operate without
containment and ventilation structures also allowed more lanes to
remain operable during deleading and repainting activities. Unusually
heavy weekend traffic, returning late from the Jersey shore, prompted
a request for rapid demobilization to free-up a lane of traffic--and
the entire system, crew, and trucks were safely off the roadway
in 15 minutes.
Tool operators
in high lift trucks with 50 ft. reaches were situated on either
side of the bridge. Workers attacked the I-beams with ROTO-PEEN
Scalers and CORNER-CUTTER
needle guns. The former evacuated power tool cleans flat steel to
a bare metal finish, while the latter has interchangeable shrouds
permitting access to tight corners, edges, and around bearings.
All coatings
were removed by the 100 percent mechanical system and conveyed directly--via
hoses up to 200 ft. in length--into a 55-gallon drum integral to
the VAC-PAC unit, which seals the waste under negative pressure
for a dustless changeout. After an area was deleaded, the crew immediately
applied primer to protect the bare metal surface. The specified
coating system consisted of two coats of aluminum epoxy mastic and
a urethane finish. An epoxy waterproof seal coat was applied to
the concrete abutments.
A previous demonstration for the NJ DOT of the cleanliness of Pentek's
lead abatement system, buttressed by historical results, provided
CRX technicians with the performance data necessary to forego burdensome
respiratory gear. This increased productivity up to 50 percent per
day in the hot, humid summer working conditions. Costs for OSHA-mandated
health and safety requirements were likewise minimized. Post-project
blood-lead level results for CRX workers averaged under 9 micrograms/dL,
far below OSHA's regulatory limit of 40 micrograms/dL. Pentek's
integrated removal system allowed CRX to finish the project well
within schedule constraints. "The abatement system and repainting
operation were excellent," said the principle bridge engineer
for NJ DOT. Pentek's lead abatement system proved it is a viable,
cost-effective alternative to abrasive blasting when erection of
containment structures is cost prohibitive or logistically unfeasible.