Pentek Lead Abatement System Employed at Consolidated Edison

    by Brad Fuller


When Consolidated Edison Company of New York released job specifications for contractor bidding on the lead removal from their 125 foot-high steam dispersion stacks at the 1551 megawatt Astoria Power Generating Station, it was pointedly clear no lead would be released into the air during the project. If abrasive blasting were chosen for surface preparation, state-of-the-art full containment would have to be used, complete with air-tight seals, ventilation systems, entrance and exit air locks, and impermeable containment material to ensure minimal discharge on the power generating plant below the stack. The contractor would also be required to meet all OSHA requirements, such as medical surveillance, hygiene facilities, separate eating areas, and personal protective equipment if lead levels exceeded 30 micrograms per cubic meter.

To reduce the additional costs of erecting and maintaining full containment without jeopardizing health and safety criteria, Con Ed incorporated a practical solution to remove their aging lead-based paint. Nelson Maintenance Services, Inc. of Yonkers, NY bid the project incorporating Pentek's integrated lead abatement system. Pentek's system consists of the VAC-PAC high performance, self-drumming HEPA filtration system for central operations, which can support up to ten individual operators with RotoPeen Scalers and CORNER-CUTTER needleguns. The RotoPeens are excellent for flat areas, removing coatings at 45 square feet per hour, while the CORNER-CUTTERS are ideal for corners, edges, rivets, and bolts.

Nelson Maintenance assured Con Ed airborne exposures would approach zero, in compliance with all federal and state lead exposure regulations. Upon review of the bids, Nelson Maintenance was awarded the contract for lead removal on stack 50. Ramon Luis, Nelson Maintenance's project manager estimated the stack had approximately 7,500 square feet of steel.

"Even with the (New York) city's labor costs, the Pentek system provides a real competitive advantage," claimed Umberto Louis, executive vice-president of Nelson Maintenance. "If I were to incorporate abrasive blasting with full containment, my bids would be two to three times higher. Pentek's system reduces the high costs of worker and environmental protection associated with abrasive blasting by capturing the lead at the point of generation. With no escaped lead, my costs for compliance are negligible--I pass those savings on to the owner."

At the Astoria Power Generating Plant, Nelson Maintenance's crew positioned the VAC-PAC on the roof of the power generating building. Compressed air was supplied from an airline hose connected to the compressor 50 feet down at street level. The vacuum hoses extended as far as 200 feet away, eliminating the need for workers to transport individual, conventional HEPA vacuums to support the shrouded power tools. One retractable, elevated platform was incorporated to provide access to the 18-foot diameter of the stack's exterior and no containment structure was erected. As Nelson Maintenance's crew of four removed the lead-based paint, they immediately followed along with new protective coatings. The new paint system specified by Con Ed called for a Rust Barrier 55 VOC Compliant primer and a Polyon II 3900 Series Topcoat supplied by Con-Lux.

The contract allowed for 35 days to complete the project: Nelson Maintenance completed all work within 21 days, including mobilization, removal, painting, and demobilization. During abatement, an independent testing lab reviewed the project for worker and environmental safety. All airborne monitoring results were well below OSHA's action level of 30 micrograms per cubic meter on an 8-hour TWA, and ground lead samples near the site did not show any increase above background levels.

The benefits of this lead abatement system, which continue to accrue to Con Ed and the New York public it serves, are due in large measure to the foresight of Con Ed's own R&D Department. In the late 1980s, technology development and demonstration work for the VAC-PAC and CORNER-CUTTERS used on this project were jointly funded by Con Ed, the Electric Power Research Institute (EPRI), and Pentek. The research effort was aimed at finding cleaner, safer, and more effective methods to remove radiologically contaminated protective coatings at the company's Indian Point Station, a 975 MW nuclear power plant located in Westchester County. Pentek technology is now routinely employed at Indian Point as part of its ongoing coatings maintenance program, as well as on various public housing, subway, airport, and highway rehabilitation projects located throughout New York City and the metropolitan area.

[Home] [Lead] [Nuclear & Decon ] [Products] [Customer Service] [Users List] [Case Histories] [Flaps]